Highway 210 Bridge Nears Completion

By Derek Sidian Aug 21, 2026 | 7:30 AM

Crews pouring concrete on the easternmost roundabout on Highway 210. (Derek Sidian, KBRF News)

Fergus Falls, MN – Progress continues steadily on the Highway 210/I-94 Interchange Reconstruction Project as construction of the bridge nears completion.

MnDOT engineer Jesse Miller says crews are pouring concrete for the bridge railings, and after that they’ll pour the final overlay for the driving lanes.

Crews working on Highway 210 and the three roundabouts are also hard at work pouring concrete. Miller says, “The mainline concrete’s getting poured, the concrete curb, truck aprons, all that stuff’s getting poured. So there’s a lot of activity out there right now.”

Regarding the on/off-ramps, Miller says crews have poured the eastbound off-ramp and are going to start the westbound on-ramp in the coming days.

Drivers are reminded to be cautious and drive safe when going through the work zone.